set reserve_schedule_penalty_cost

iLab Assistant

Command to set the penalty cost for breaking the unit reserve schedule constraints. Default value is 10000 NOK/MW

Options
Valuedouble
LicenseSHOP_RESERVE_GROUP
Release version13.0.0.a

Reserve group schedule penalty cost

If the reserve group schedule is not fulfilled, a penalty cost will be applied. This cost can be set with the command:

set reserve_schedule_penalty_cost <value>